The actual ground-breaking began a few weeks ago, when DeRita Construction and KBE Building Corporation began to level the land for construction.




By SLOAN BREWSTER, Press staff
MIDDLETOWN — The U.S. Army Reserve is seeking a permit to
fill wetlands at Cucia Park. The federal permit from the U.S. Army Corps
of Engineers is part of the Clean Water Act, and one of the legal hurdles the
military must jump in its plans to build an army reserve training center on
the 42-acre park on Smith Street. In July, Mayor Sebastian N. Giuliano
signed the contract for the $2 million sale of the park. Now he is waiting
for the money, he said Tuesday. According to the contract, the military has
until the end of the fiscal year to pay. Last month at the Crowne Plaza
Hotel in Cromwell, the buyers held a preconstruction meeting with
contractors that might be interested in building the proposed facility, the
mayor said. Construction on the three-story, 164,007-square-foot facility on
17 acres of the park will not begin until the permit is issued, said Todd
Hornback, Corps spokesman for the Louisville District. “Once the permit goes
through, we can finalize the contract,” Hornback said. The permit will limit
what can be done on the wetlands, said Larry Rosenberg, corps chief of
public affairs for the New England District. “We have to gain that permit to
see what mitigation [allows], and how much can we fill,” he explained. In
order to make such determinations, the corps must evaluate the construction
plans and consider the impact to the wetlands, Rosenberg said. “Our goal is
always net loss zero,” Rosenberg said. “The only thing that we issue a
permit on is the least damaging practicable alternative. This is a public
trust; we are charged by congress to not impact on the environment
negatively.” There have already been changes to the plans for the wetlands,
Hornback and Rosenberg said, specifying that the amount to be filled has
been decreased. Neither spokesman knew the exact specifications of the
changes, they said. The permit can be denied, issued or issued with
conditions, Rosenberg said, adding that 99 percent of such permits are
issued with conditions. The training center is a response to the 2005 Base
Realignment and Closure Act, which mandates smaller individual reserve bases be closed and replaced with larger combined locations where reservists train on alternate weekends. There is a 30-day period during which the public may file comments or request a public hearing on the permit review. Public comments must be filed no later than Sept. 11, to the U.S. Army Corps of
Engineers, New England District, Regulatory Division, (attn: Cori Rose) 696
Virginia Road, Concord, MA 01742-2751, or e-mail cori.m.rose@usace.army.mil.

Close the US Army Reserve Center, Middletown, CT, ... and relocate units to a new Armed Forces Reserve Center ... in Middletown, CT, if the Army is able to acquire land suitable for the construction of the facilities. [emphasis mine, some of Blumenthal's comments pertain to this, see below]Second, Colonel Landry announced that all three of the remaining sites under consideration, Cucia Park, Bysiewicz Industrial Park, and Boardman Lane/Ken Dooley Drive, would be evaluated in equal measure. A final decision on a site will not be made until after completion of Environmental and Engineering
*17 October - Complete Draft Site Identification Report and forward for approvalIn a call with Diane McCartin (Middletown AFRC project manager) and Ron Elliot (ACE public affairs specialist) today, I asked whether they had made any progress towards the release of ranked sites. To my surprise, Ms. McCartin told me, "I don't believe there is a ranked list of sites." Apparently, no such ranking will be determined until next March or April, when the draft Environmental Assessment will be made available to the public for a 30 day comment period.
*Early November - Release ranked sites; NEPA and real estate process continues
*March 2009 - Contract ready to advertise
*June 2009 - Contract Award
However, the Army Corps will return to Middletown on Monday, November 10th, for a Press event. Mr. Elliot indicated that Colonel Keith Landry, commander of the Louisville District of the Corps, would be joining the civilian staff from the Corps at this press event. Its purpose is to "tell people exactly where we're at in the process [of choosing a site]," according to Mr. Elliot. A media advisory will be sent out on Friday to announce the time, location, and format (press release or press conference) for the event. Neither Mr. Elliot nor Ms. McCartin could be specific about what sort of information would be provided that was not already provided in previous meetings and press conferences.Cucia Park:
Ken Dooley/Boardman Lane:
Mile Lane:
After this basic summary of the feedback each site has received, residents were able to comment on each site. These comments were videotaped and also annotated by a court reporter for inclusion in the official record.
The only comment on the Bysiewicz Industrial Park was from the owner of the brick home that would be surrounded on 3 sides by the base: he will offer his home for sale to the Army should this site be chosen. (This house would make a stately home for the Base Commanding Officer, so I recommend that he hold out for top dollar should it come to that...)
Several residents from Smith Street and the Westlake area made surprisingly strong comments AGAINST the use of Cucia Park. Most of the comments referenced how nice the park used to be and chided the city for not taking care of it. Councilman Klattenberg clarified that Cucia Park is actually about 4.4 acres contiguous to about 36 acres of abandoned industrial land (a former brick yard). The Mayor's Advisory Panel already inquired about preserving public access to the pond, and the Army has promised to take that under consideration.
Stephen Devoto, on behalf of the Westfield Residents Association, spoke specifically about the 3 possible sites that are in Westfield (KD/Boardman Lane, Bysiewicz Industrial Park, and Cucia Park). Ranking Cucia Park as the best choice, Devoto stated that the WRA is not thrilled about the city selling a park. However, given the extreme circumstances (and the fact that the Army SHOULDN'T be looking for land in Middletown ever again) the use of Cucia Park brings the most benefit to the city with the least amount of harm to residential neighborhoods. Devoto also commented that WRA's passionate involvement in the site selection process doesn't come from NIMBY (not in my backyard) concerns: rather, the passion comes from the abundance of analysis that the WRA has conducted since June, and the conviction that IF the Army has to build in Middletown, it should value above all else what the town thinks is the best site.
Mayor Guiliano spoke plainly and simply about the KD/Boardman Lane and Cucia Park sites. He asked the audience to consider for a moment that a private developer had submitted the Army's plans: in the case of Boardman Lane, the Mayor was "pretty confident" that those plans would be denied, just as he was confident that the same plans for Cucia Park would be approved. Guiliano told the Army to keep in mind that the Boardman Lane/KD site asked the city to accept something it wouldn't accept from any private entity. (Way to go, Mayor!!!)
After other comments on public safety issues, traffic concerns, and the danger of a schedule determining the sites available for consideration, Councilman Klattenberg mentioned that the Common Council will be taking up a resolution at its next meeting (Monday, October 6th) that endorses the use of Cucia Park and directs the City's Economic Development Commission to begin the process to dispose of the property as necessary. The Councilman also compared the Army's "open and collaborative" process to a funny joke about a neighbor listening to a husband and wife argue. At a point late in the evening, the arguing suddenly stopped, and when the neighbor later asked the wife what happened, she replied that her husband had agreed to a compromise: he agreed with her position.
That's where I'm at. I'm ready for the Army to catch a clue and to agree with the town's position on Cucia Park. David Dale's response to Councilman Klattneberg's comments was a polite "thank you for your comments" response, but I really wanted a simple "Yes, Dear." Of course I understand why he couldn't say that, but I'm ready to move on to other things (like maybe the bus issue and how the Board of Education has rocks for brains when it comes to imagining what parents are going through because of the new busing policy...oh, wait, that's something for another time...).
A brief on-the-way-out-the-door conversation with the Army's architect enlightened my suffering in a way I hadn't considered before. Until the NEPA process kicks in for the 4 sites (that's about the beginning of November), the Army is only about cost, engineering considerations and site availability. The public passion for or against a particular site doesn't come to bear on the decision making process UNTIL the NEPA considerations are factored in.
Wait for it...yes...read those two sentences again...yes, I can see the light bulb turning on above your head. If all the public comments for or against a specific side aren't evaluated and factored into the selection process until NOVEMBER at the earliest, what on earth have we been doing for the last 3 months? I was assured that the public comments made on the blog and recorded during tonight's meeting are now part of the official "stuff" that will be looked at during the NEPA review, so yeah for everyone who took the time to give their opinions. However, I was under the impression that since so many of us (elected officials too) have been saying the same thing for so long, that the sustained and vigorous protest against the Boardman Lane site (no matter how you access it) would have affected the narrowing process that whittled 16 sites down to 4. But no. I was wrong. The only factors that appear to have caused properties to fall out of contention were cost-related - both time and money. A perfect site may have been dropped because it was too costly to develop or because it would take to long to figure out how to develop it. Meanwhile, a perfectly horrible site is preserved just because guestimated engineering costs fall within the allowed budget.
Yes, I do understand this is the real world, and that the ideal isn't always possible. However, as the presidential candidates keep reminding us, Main Street is supposed to matter. We the people gave our government the power it needs to function, we the people pay for that functioning, and we the people ought to BENEFIT from that functioning. Abraham Lincoln said that the "legitimate object of governments is to do for a community of people, whatever they need to have done, but cannot do at all or cannot, so well do for themselves - in their separate and individual capacities." As a nation, we've agreed to separate that doing into local, state and federal responsibilities, and I don't think anyone is challenging the basic need for an Army Reserve Training Center. But in THIS case, THIS community of people CAN decide what needs to be done, and the federal government ought to take heed. Our federal tax dollars will pay for this new facility, and how rude it will be to suffer a site chosen despite strong and sustained resident and local elected officials' opposition.
So, the end really isn't the end yet. The public comment period for the site selection list is closed, but we learned tonight that what REALLY counts is the 30 day public comment period on the NEPA process/results. That won't start until at least November. Right. See what I mean about tiring and exhausting? Just as Christmas is approaching, and I'm betting that this holiday season will be hard for a lot of families, we still won't have resolved the issue of where this base is supposed to go. Maybe I'll start on an updated version of the Grinch who stole Christmas...

News and questions.
m a brick manufacturing company in 1974, and dedicated as a park in 1975.
The Army is requesting site suggestions from community members, city officials and state agencies. The U.S. Army Corps of Engineers website will accept site recommendations for the project.
The Army is asking community members to recommend sites and comment by Sept. 29.
This meeting will be moderated by State Legislator Ray Kalinowski. It will be a public hearing, members of the public are invited to speak regarding the proposed training facility.
Today's Hartford Courant lead editorial (I've only changed the formatting)